  1. 7/3/2008 PLATTE CANYON WATER MAIN REPLACEMENT WORK SET TO BEGIN
  2. Platte Canyon will be conducting three major water construction projects this summer.  On June 27th the Board of Directors awarded the construction contracts for these projects to Levi Contractors.
     
    The projects are:
     
    South Depew Street Water Main Replacement
     
    695 feet of 8-inch water pipe will be replaced in S. Depew St., between W. Coal Mine Ave. and W. Ontario Ave. in the Normandy Estates Subdivision.  Work is expected to begin July 21, 2008 and will continue for approximately one month.  The project is expected to cost $97,095.
     
    Addresses that are projected to be affected by this project include:
     
              6850 S. Depew St.           6715 S. Depew St.
              6780 S. Depew St.           6735 S. Depew St.
              6760 S. Depew St.           6755 S. Depew St.
              6740 S. Depew St.           6825 S. Depew St.
              6730 S. Depew St.           6845 S. Depew St.
              6705 S. Depew St.           5490 W. Coal Mine Ave.
     
     
    Dutch Creek Drive Water Main Replacement
     
    796 feet of 6-inch water pipe will be replaced in Dutch Creek Dr. between Meadowlark Ln. and Glenridge Dr. in the Columbine Heights Subdivision. Work is expected to begin August 4, 2008 and will continue for approximately one month.  The project is expected to cost $114,610.
     
    Addresses that are projected to be affected by this project include:
     
              #1 Dutch Creek Dr.           #11 Meadowlark Ln.
              #3 Dutch Creek Dr.           #12 Robincrest Ln.
              #5 Dutch Creek Dr.           #11 Robincrest Ln.
              #7 Dutch Creek Dr.           #12 Glenridge Dr.
              #9 Dutch Creek Dr.           #11 Glenridge Dr.
              #11 Dutch Creek Dr.
     
     
    West Hinsdale Circle Main Rehabilitation
     
    1,215 feet of 6-inch water pipe will be replaced in W. Hinsdale Cir. between S. Platte Canyon Dr. (south intersection) and S. Platte Canyon Dr. (north intersection) in the Columbine Manor Subdivision. Work is expected to begin August 18, 2008 and will continue for approximately one month.  The project is expected to cost $124,935.
     
    Addresses that are projected to be affected by this project include:
     
              5005 W. Hinsdale Cir.           5138 W. Hinsdale Cir.
              5012 W. Hinsdale Cir.           5148 W. Hinsdale Cir.
              5025 W. Hinsdale Cir.           5127 W. Hinsdale Cir.
              5035 W. Hinsdale Cir.           5117 W. Hinsdale Cir.
              5045 W. Hinsdale Cir.           5107 W. Hinsdale Cir.
              5055 W. Hinsdale Cir.           5066 W. Hinsdale Cir.
              5065 W. Hinsdale Cir.           5046 W. Hinsdale Cir.
              5075 W. Hinsdale Cir.           5026 W. Hinsdale Cir.
              5108 W. Hinsdale Cir.           5006 W. Hinsdale Cir.
              5118 W. Hinsdale Cir.           7307 S. Platte Canyon Dr.
              5128 W. Hinsdale Cir.           7327 S. Platte Canyon Dr.
     
     
    To view the location maps for these projects and access the project status pages please visit the Current Project page by clicking here.  Updated project details will be posted to the project status pages as they become available.
     
    If you do not have the time to check for project updates you can choose to register for the District’s Email Update Service.  By registering for this free service you will receive automatic updates when the project status is changed.  For more information about this service please click here.
     
    If you have any questions or comments concerning any of these projects, please contact Denny Morse, Construction Manager, at 303-979-2333.